# Kanban Board and WIP Limits

> How Kanban shows work on a board and caps how much is in progress at once. Why a WIP limit makes a team finish more by starting less.

**Course:** [Agile, Scrum and Kanban](https://learn.benibix.com/learn/business-agile)  
**Time:** 11 min

**After this lesson you can:**

- Set up a simple Kanban board
- Set a WIP limit for a column
- Explain how a pull system works

## How a Kanban board and a WIP limit work

Kanban is a method for managing how work flows. The team shows every step of its work on a board and caps how much can be in progress at once. It has no sprints and no set roles. Work starts when there is room and finishes when it is done. A cap of 3 items in testing is a typical rule.

A Kanban board has one column for each step of the work. A simple one has to do, doing and done. Real boards add steps such as review and test. Each piece of work is a card that moves from left to right. One look shows where everything is.

A work in progress limit, or WIP limit, caps how many cards one column can hold. When review is full at 2 cards, nobody moves a third card into it. Instead, people help finish what is already there. That is the rule that makes Kanban work.

It feels slower, and it is faster. A person juggling five tasks finishes each one late, because they keep switching. Three people each holding one task finish sooner. Starting less means finishing more.

A WIP limit turns the board into a pull system. People pull new work into their column only when they have room. Nobody pushes work onto someone who is already full. The idea came from car factories in Japan, where a step made parts only when the next step asked for them.

The limits also show where work gets stuck. If the test column is always full and the build column is always waiting, testing is the slow step. The team can then help test, or add a tester, instead of building more work that will only wait.

The common mistake is a board with no limits. It looks like Kanban, but it is a to-do list on a wall. Cards pile up in doing, everyone is busy and little gets finished. Set a limit, even a loose one, and tighten it.

![A board with four columns: to do, doing with a limit of 3, review marked 2 of 2, full, and done. The doing column has room for one more card. An arrow marked pull shows a card being taken from to do into doing.](https://learn.benibix.com/diagrams/agile-kanban-board.svg)

### Example: Lucy's support team sets a limit

Lucy's support team of 4 in Manila has 18 cards in doing, and the average fix takes 9 days. Everyone is busy.

They set a limit of 6 cards in doing. People finish before they start. After a month the average fix takes 4 days, and they close more cards each week than before.

**Words in this lesson:** [Kanban](https://learn.benibix.com/term/business/kanban), [Kanban Board](https://learn.benibix.com/term/business/kanban-board), [Work in Progress Limit](https://learn.benibix.com/term/business/wip-limit), [Pull System](https://learn.benibix.com/term/business/pull-system)

**Question:** The review column is at its WIP limit. What should a team member with free time do?

**Answer:** Help finish a card already in review. A full column means finish before you start. Helping clear review frees room for new work. Starting more would only add to the queue.

---

Source: https://learn.benibix.com/learn/business-agile/kanban-board-and-wip-limits
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.