# The Project Manager Role

> What a project manager does each week, and what they answer for. How a project coordinator helps, and where the line between the two jobs sits.

**Course:** [Project Management Basics](https://learn.benibix.com/learn/business-project-management)  
**Time:** 10 min

**After this lesson you can:**

- Describe a project manager's week
- Say what a project manager answers for
- Tell a coordinator's job from a manager's

## What a project manager does all week

A project manager is the one person who runs a project day to day and answers for its result. On a team of 12, they rarely do the hardest task themselves. Their week goes on planning, checking progress and clearing problems. They also keep people told what they need to know.

Planning comes first. They break the goal into tasks, put the tasks in order and match each one to a person. Then they check, often every week, whether the work is where the plan said it would be.

Much of the job is talk. A project manager talks to the team, to the person paying, to suppliers and to the people who will use the result. Good news can wait for a weekly note. Bad news is worth a phone call the same day.

When something breaks, they fix it or pass it up. A late supplier, a sick team member or a new request all land on their desk. They cannot solve everything, but they must know who can, and ask fast.

A project coordinator helps with the daily details. They book the meetings, take the notes, track the tasks and chase late updates. They keep the files and the dates up to date. They work for the project manager and make fewer of the big calls.

The line between the two jobs is the result. The coordinator keeps the day in order. The project manager answers for whether the project lands. Many managers start out as coordinators. They learn the job by watching it up close.

The common mistake is choosing the best expert on the team as project manager. Being the best coder or builder is a different skill. The job is to lead the work and make choices, not to do the hardest task.

![The sponsor sits at the top, with money and the reason for the project. Below is the project manager, who runs the work, with the coordinator beside them. The team sits at the bottom. To the right, outside the project, the PMO sets the rules for this project and the others.](https://learn.benibix.com/diagrams/pm-roles.svg)

### Example: Jack's office move in Singapore

Jack runs the move to a new office in Singapore. He has 12 people, 3 suppliers and a budget of 300,000 dollars.

Emma, his coordinator, sends the notes from each meeting within the hour and chases 4 late tasks a week. When the desk supplier slips by 2 weeks, Jack is the one who decides what to do.

**Words in this lesson:** [Project Manager](https://learn.benibix.com/term/business/project-manager), [Project Coordinator](https://learn.benibix.com/term/business/project-coordinator)

**Question:** What does a project manager answer for?

**Answer:** Whether the project delivers its result. The project manager owns the result, though the team does most of the work. Notes are the coordinator's job. The money comes from the sponsor.

---

Source: https://learn.benibix.com/learn/business-project-management/project-manager-role
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.