# Budget at Completion (BAC)

> The total budget for all the planned work. It is where the plan ends up.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** BAC

## Think of it like

It is like the price on the ticket before a trip. It is what you plan to pay in all.

## Definition

Budget at completion, or BAC, is the total budget for all the planned work on a project. It is the top of the planned value line, reached on the last day. If a project plans to spend 100,000 dollars on its work, its BAC is 100,000 dollars. It leaves out the management reserve. It only changes when an approved change moves the plan.

## Example

Lucy's office move has a BAC of 120,000 dollars. Halfway through, her forecast says 132,000, so she is heading 12,000 over.

## Why it matters

Each guess of the final cost starts from it. With no fixed total, there is nothing to hold an overrun up to.

## Common mistake

Adding the management reserve to it. That money sits outside the plan. The project then looks on budget while it eats the reserve.

## Three principles

- **The whole plan.** All the planned work, added up.
- **Fixed.** It changes only through an approved change.
- **Start of the forecast.** The final cost forecast divides it by the CPI.

## Related terms

- [Earned Value Management (EVM)](https://learn.benibix.com/term/business/earned-value-management)
- [Planned Value (PV)](https://learn.benibix.com/term/business/planned-value)
- [Estimate at Completion (EAC)](https://learn.benibix.com/term/business/estimate-at-completion)
- [Cost Performance Index (CPI)](https://learn.benibix.com/term/business/cost-performance-index)
- [Project Budget](https://learn.benibix.com/term/business/project-budget)

## Told apart from

- [BAC vs EAC](https://learn.benibix.com/compare/budget-at-completion-vs-estimate-at-completion): People think the EAC is just the budget. It is not. The BAC is the budget, the total of the plan, and it stays fixed. The EAC is today's guess of what the whole project will cost. It moves with every report.

![Three lines rise over time against money. The planned value curve rises in an S shape to the total budget at the end. At a line marked today, the actual cost line sits above the earned value line, and both sit below planned value. A dashed line runs on from actual cost to a point above the budget, marked estimate at completion.](https://learn.benibix.com/diagrams/pm-earned-value.svg)

---

Source: https://learn.benibix.com/term/business/budget-at-completion
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.