# Burnup Chart

> A chart of work done climbing toward a scope line. It shows when scope changes.

**Field:** Business & Startups  
**Category:** Agile Delivery  
**Also known as:** Burn-Up Chart, Release Burnup

## Think of it like

It is like climbing to a flag on a hill. If someone moves the flag higher, you can see it.

## Definition

A burnup chart shows work done rising over time. It has two lines. One climbs as work is finished. The other shows the total scope. When the two lines meet, the work is done. Because scope has its own line, you can see when work is added or taken away.

## Example

A release starts at 60 points and grows to 80 in sprint 4. The done line climbs 10 points a sprint and meets the scope line in sprint 8.

## Why it matters

It splits two things a burndown mixes up: the team is slow, or the work grew. Stakeholders see why a date moved.

## Common mistake

Drawing it without the scope line. Then it only counts work done and hides the very thing it is for.

## Three principles

- **Two lines.** One for work done, one for scope.
- **Scope is in view.** Added work shows as a jump.
- **Done where they meet.** The finish is where the lines touch.

## Related terms

- [Burndown Chart](https://learn.benibix.com/term/business/burndown-chart)
- [Release Planning](https://learn.benibix.com/term/business/release-planning)
- [Velocity](https://learn.benibix.com/term/business/velocity)
- [Scope Creep](https://learn.benibix.com/term/business/scope-creep)
- [Story Points](https://learn.benibix.com/term/business/story-points)

## Told apart from

- [Burndown Chart vs Burnup Chart](https://learn.benibix.com/compare/burndown-chart-vs-burnup-chart): People think the two charts show the same thing. A burndown counts work left and falls to zero. A burnup counts work done and climbs to a scope line. Only the burnup shows when work is added, so a flat burndown can hide a team that is working hard.

## Taught in

- [Velocity and Burndown Charts](https://learn.benibix.com/learn/business-agile/velocity-and-burndown-charts): Agile and Scrum, 16/19

![A chart with points on the up axis and 8 sprints along the bottom. A grey line near the top is the total scope: it starts at 60 and jumps to 80 in sprint 4, marked scope added. A rising line in the accent colour is work done. It climbs 10 points each sprint and meets the scope line in sprint 8.](https://learn.benibix.com/diagrams/agile-burnup.svg)

---

Source: https://learn.benibix.com/term/business/burnup-chart
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-17
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.