# Cost Variance (CV)

> Earned value take away actual cost. Less than zero means you spent too much.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** CV

## Think of it like

It is like buying 20 dollars of food and paying 25. You went 5 over.

## Definition

Cost variance shows whether a project is under or over budget for the work done. You find it by taking actual cost away from earned value. A negative number means the work cost more than planned. A positive number means it cost less. It is one of the clearest early signs of money trouble.

## Formula

```
CV = EV - AC
```

## Example

Earned value is 30,000 dollars and actual cost is 36,000. Cost variance is minus 6,000 dollars, so the work is over budget.

## Why it matters

Overspend early in a project rarely fixes itself. This number spots it while there is time to act.

## Common mistake

Comparing spend with planned value instead of earned value. That mixes up being late with being over budget.

## Three principles

- **EV minus AC.** Value done against money spent.
- **The sign matters.** Negative is over budget.
- **Act early.** Small gaps grow.

## Related terms

- [Cost Performance Index (CPI)](https://learn.benibix.com/term/business/cost-performance-index)
- [Schedule Variance (SV)](https://learn.benibix.com/term/business/schedule-variance)
- [Earned Value (EV)](https://learn.benibix.com/term/business/earned-value)
- [Actual Cost (AC)](https://learn.benibix.com/term/business/actual-cost)

![Three lines rise over time against money. The planned value curve rises in an S shape to the total budget at the end. At a line marked today, the actual cost line sits above the earned value line, and both sit below planned value. The gap between earned value and planned value is marked schedule variance, and the gap between earned value and actual cost is marked cost variance. A dashed line runs on from actual cost to a point above the budget, marked estimate at completion.](https://learn.benibix.com/diagrams/pm-earned-value.svg)

---

Source: https://learn.benibix.com/term/business/cost-variance
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.