# Crashing

> Adding people or money to the key tasks. Then they finish sooner.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** Project Crashing, Schedule Crashing

## Think of it like

It is like asking friends to help you clean your room. It goes faster, but you owe them a treat.

## Definition

Crashing shortens a schedule by adding people, money or tools to tasks on the critical path. It keeps the order of the tasks the same. Each day saved costs extra, so you crash the cheapest tasks first. At some point more people stop helping and only add cost. It works best on tasks that can be split between many hands.

## Example

A team pays for weekend shifts on the build task. It ends 5 days sooner and costs 8,000 euros more.

## Why it matters

It buys time with money, when the date matters more than the budget.

## Common mistake

Adding people late to work that cannot be split. New people need training and can slow the team down.

## Three principles

- **Pay for time.** Each day saved costs more.
- **Cheapest first.** Crash the least costly task.
- **Critical path only.** Other tasks gain nothing.

## Related terms

- [Schedule Compression](https://learn.benibix.com/term/business/schedule-compression)
- [Fast-Tracking](https://learn.benibix.com/term/business/fast-tracking)
- [Critical Path](https://learn.benibix.com/term/business/critical-path)
- [Project Budget](https://learn.benibix.com/term/business/project-budget)

## Told apart from

- [Fast-Tracking vs Crashing](https://learn.benibix.com/compare/fast-tracking-vs-crashing): People think fast-tracking and crashing are the same trick. Both shorten the critical path. Fast-tracking runs tasks at the same time that were planned one after another, which adds risk. Crashing adds people or money to a task so it ends sooner, which adds cost.

![Three rows of two bars over a line of days. Normal: design, then build, one after the other. Fast-tracking: build starts before design ends, and the overlap is marked risk. Crashing: design, then a shorter build bar marked extra people and extra cost. Both lower rows end sooner than the first.](https://learn.benibix.com/diagrams/pm-compression.svg)

---

Source: https://learn.benibix.com/term/business/crashing
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.