# Cumulative Flow Diagram (CFD)

> Stacked bands, one per step of the work, drawn over time. A band that widens shows a jam.

**Field:** Business & Startups  
**Category:** Agile Delivery  
**Also known as:** CFD, Cumulative Flow Chart

## Think of it like

It is like a cake with layers that keep growing. A fat layer means work is piling up in that step.

## Definition

A cumulative flow diagram shows how many items sit in each step of the work, day by day. Each step, like to do, doing and done, is a band stacked on the others. The done band at the bottom grows as work finishes. The height of a middle band is the work in progress there. Its width across shows about how long items take. A band that keeps getting wider means work is piling up in that step.

## Example

Emma's team sees its review band grow fatter every week for a month. Items are waiting for review, so two people help with reviews for a week.

## Why it matters

One picture shows work in progress, throughput and delays all at once. A jam is visible before anyone complains.

## Common mistake

Reading it like a burnup chart. The top line is work coming in, and the flow lives in the gaps between the bands.

## Three principles

- **One band per step.** Each column on the board gets a band.
- **Height is work in progress.** Measure a band straight up.
- **Width is time.** Measure across to see how long items take.

## Related terms

- [Kanban](https://learn.benibix.com/term/business/kanban)
- [Throughput](https://learn.benibix.com/term/business/throughput)
- [Cycle Time](https://learn.benibix.com/term/business/cycle-time)
- [Work in Progress Limit](https://learn.benibix.com/term/business/wip-limit)
- [Burnup Chart](https://learn.benibix.com/term/business/burnup-chart)

## Taught in

- [Lead Time and Cycle Time](https://learn.benibix.com/learn/business-agile/lead-time-and-cycle-time): Agile and Scrum, 11/19

![A chart of three stacked bands over ten weeks. The bottom band, in the accent colour, is done and grows steadily. Above it sits a band for doing, then a band for to do on top. A short arrow straight up through the doing band is marked work in progress. An arrow across the same band is marked about how long items take.](https://learn.benibix.com/diagrams/agile-cfd.svg)

---

Source: https://learn.benibix.com/term/business/cumulative-flow-diagram
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-17
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.