# Earned Value Management (EVM)

> A way to track a project's time and cost. It compares three numbers.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** EVM, Earned Value Analysis

## Think of it like

It is like checking a road trip halfway. You look at how far you drove, how far you planned, and how much fuel you used.

## Definition

Earned value management, or EVM, measures a project's progress using money. It compares three numbers at any date. Planned value is the work that should be done by now. Earned value is the work that is done. Actual cost is what that work really cost. From these you can tell if the project is behind, over budget or both.

## Example

At month three, Jack's project shows planned value 40,000, earned value 30,000 and actual cost 36,000. It is behind and over budget.

## Why it matters

Budget spent tells you nothing alone. EVM shows what you got for the money.

## Common mistake

Comparing spend with the plan and skipping earned value. A project can be on budget only because it has done less.

## Three principles

- **Three numbers.** Planned value, earned value and actual cost.
- **One unit.** Time and cost both measured in money.
- **Early warning.** Shows trouble weeks ahead.

## Related terms

- [Planned Value (PV)](https://learn.benibix.com/term/business/planned-value)
- [Earned Value (EV)](https://learn.benibix.com/term/business/earned-value)
- [Actual Cost (AC)](https://learn.benibix.com/term/business/actual-cost)
- [Cost Performance Index (CPI)](https://learn.benibix.com/term/business/cost-performance-index)
- [Schedule Performance Index (SPI)](https://learn.benibix.com/term/business/schedule-performance-index)

![Three lines rise over time against money. The planned value curve rises in an S shape to the total budget at the end. At a line marked today, the actual cost line sits above the earned value line, and both sit below planned value. The gap between earned value and planned value is marked schedule variance, and the gap between earned value and actual cost is marked cost variance. A dashed line runs on from actual cost to a point above the budget, marked estimate at completion.](https://learn.benibix.com/diagrams/pm-earned-value.svg)

---

Source: https://learn.benibix.com/term/business/earned-value-management
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.