# Earned Value (EV)

> The budget for the work that is really done so far.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** EV, Budgeted Cost of Work Performed, BCWP

## Think of it like

It is like counting the pages you have really read. It does not matter how long it took.

## Definition

Earned value is the budget for the work that is actually finished. You find it by multiplying the share of work done by the total budget. If a 100,000 dollar project is 30% done, its earned value is 30,000 dollars. It does not care what was spent. It only measures what was achieved.

## Formula

```
EV = % of work complete x BAC, the budget for all the work
```

## Example

A 100,000 dollar project is 30% done. Its earned value is 30,000 dollars, whatever was spent.

## Why it matters

It turns progress into money, so it can be compared with both the plan and the spend.

## Common mistake

Calling it the money spent. Earned value counts work done, at its planned price.

## Three principles

- **Work done.** Only finished work counts.
- **Planned price.** Valued at its budget, not its cost.
- **The middle number.** Compared with plan and spend.

## Related terms

- [Earned Value Management (EVM)](https://learn.benibix.com/term/business/earned-value-management)
- [Planned Value (PV)](https://learn.benibix.com/term/business/planned-value)
- [Actual Cost (AC)](https://learn.benibix.com/term/business/actual-cost)
- [Cost Performance Index (CPI)](https://learn.benibix.com/term/business/cost-performance-index)

## Told apart from

- [Earned Value vs Actual Cost](https://learn.benibix.com/compare/earned-value-vs-actual-cost): People think earned value is the money spent so far. Actual cost is the money spent. Earned value is what the finished work was planned to cost. When actual cost is higher than earned value, the work is costing more than it should.
- [Planned Value vs Earned Value](https://learn.benibix.com/compare/planned-value-vs-earned-value): People think earned value is the money earned or the work planned. It is neither. Planned value is the budget for the work that should be done by now. Earned value is the budget for the work that is really done. The gap between them shows if the project is behind.

![Three lines rise over time against money. The planned value curve rises in an S shape to the total budget at the end. At a line marked today, the actual cost line sits above the earned value line, and both sit below planned value. The gap between earned value and planned value is marked schedule variance, and the gap between earned value and actual cost is marked cost variance. A dashed line runs on from actual cost to a point above the budget, marked estimate at completion.](https://learn.benibix.com/diagrams/pm-earned-value.svg)

---

Source: https://learn.benibix.com/term/business/earned-value
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.