# Estimate at Completion (EAC)

> A guess of what the whole project will cost by the end.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** EAC

## Think of it like

It is like spending half your pocket money in one week. You can guess it will run out before the month ends.

## Definition

Estimate at completion is the forecast of what the whole project will cost when it is done. The common way divides the total budget by the cost performance index. This assumes the project keeps spending at today's rate. If a 100,000 dollar project has an index of 0.83, it will cost about 120,000. Other formulas assume the rest of the work goes to plan.

## Formula

```
EAC = BAC / CPI, where BAC (budget at completion) is the budget for all the work
```

## Example

The budget is 100,000 dollars and the index is 0.83. The forecast is 100,000 / 0.83, about 120,000 dollars.

## Why it matters

It tells leaders early how much more money to find. They learn it before the money runs out.

## Common mistake

Keeping the original budget as the forecast. If the index is below 1, the end cost will be higher.

## Three principles

- **Forecast.** The likely final cost.
- **Today's rate.** The common formula assumes it holds.
- **Update it.** Work it out again at every report.

## Related terms

- [Cost Performance Index (CPI)](https://learn.benibix.com/term/business/cost-performance-index)
- [Earned Value Management (EVM)](https://learn.benibix.com/term/business/earned-value-management)
- [Project Budget](https://learn.benibix.com/term/business/project-budget)
- [Actual Cost (AC)](https://learn.benibix.com/term/business/actual-cost)
- [Budget at Completion (BAC)](https://learn.benibix.com/term/business/budget-at-completion)

## Told apart from

- [BAC vs EAC](https://learn.benibix.com/compare/budget-at-completion-vs-estimate-at-completion): People think the EAC is just the budget. It is not. The BAC is the budget, the total of the plan, and it stays fixed. The EAC is today's guess of what the whole project will cost. It moves with every report.

![Three lines rise over time against money. The planned value curve rises in an S shape to the total budget at the end. At a line marked today, the actual cost line sits above the earned value line, and both sit below planned value. The gap between earned value and planned value is marked schedule variance, and the gap between earned value and actual cost is marked cost variance. A dashed line runs on from actual cost to a point above the budget, marked estimate at completion.](https://learn.benibix.com/diagrams/pm-earned-value.svg)

---

Source: https://learn.benibix.com/term/business/estimate-at-completion
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.