# Program Evaluation and Review Technique (PERT)

> A way to plan dates using three guesses for each task, blended into one.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** PERT, PERT Chart, PERT Method

## Think of it like

It is like asking three friends how long the drive will take. One is hopeful, one is fair and one expects jams.

## Definition

PERT is a way to plan a project's dates when task times are unsure. The name is short for Program Evaluation and Review Technique. Each task gets three guesses: best, most likely and worst. They are blended with one sum: best, plus four times likely, plus worst, divided by 6. The blended times are then joined into a chain to find the end date. It was built for the US Navy in the late 1950s.

## Example

A task could take 4, 6 or 14 days. PERT blends them into (4 + 24 + 14) / 6 = 7 days, and that 7 goes into the schedule.

## Why it matters

It shows that tasks run late more often than early. A plan built on PERT times is late less often than one built on hopeful times.

## Common mistake

Thinking PERT and CPM are rivals. They work well together: PERT blends the guesses, and the critical path is then found the same way.

## Three principles

- **Three guesses.** Best, most likely and worst for every task.
- **Weighted blend.** The most likely guess counts four times.
- **Unsure times.** It plans for tasks whose length is not known.

## Related terms

- [Three-Point Estimate](https://learn.benibix.com/term/business/three-point-estimate)
- [Critical Path Method (CPM)](https://learn.benibix.com/term/business/critical-path-method)
- [Project Estimate](https://learn.benibix.com/term/business/project-estimate)
- [Project Schedule](https://learn.benibix.com/term/business/project-schedule)

## Told apart from

- [Three-Point Estimate vs PERT](https://learn.benibix.com/compare/three-point-estimate-vs-pert): People think a three-point estimate and PERT are the same thing. A three-point estimate blends three guesses for one task. PERT is a whole way to plan the dates, built on one blend of those guesses. You can use the first without the second.

![A curve over a line of days rises fast to a peak at 6 days and trails off slowly to 14. Marks show the best case at 4, the most likely at 6 and the worst case at 14. An accent line at 7 marks the blended estimate, a little to the right of the peak.](https://learn.benibix.com/diagrams/pm-three-point.svg)

---

Source: https://learn.benibix.com/term/business/pert
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.