# Planned Value (PV)

> The budget for the work that should be done by now. It comes from the plan.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** PV, Budgeted Cost of Work Scheduled, BCWS

## Think of it like

It is like a plan that says you should read up to page 100 by Friday.

## Definition

Planned value is the budget for the work that should be done by a given date. You read it straight from the plan. If a 100,000 dollar project planned 40% of its work by month three, planned value is 40,000 dollars. Over the whole project it climbs to the full budget. It is the line every other number is compared with.

## Example

A 200,000 dollar build planned to be half done by June. Its planned value in June is 100,000 dollars.

## Why it matters

Without it, "how far along are we?" has nothing to be compared with.

## Common mistake

Mixing it up with money spent. Planned value is what the plan said, not what was paid.

## Three principles

- **From the plan.** Read off the schedule and budget.
- **Grows over time.** Climbs to the full budget.
- **The yardstick.** Earned value is checked against it.

## Related terms

- [Earned Value Management (EVM)](https://learn.benibix.com/term/business/earned-value-management)
- [Earned Value (EV)](https://learn.benibix.com/term/business/earned-value)
- [Schedule Variance (SV)](https://learn.benibix.com/term/business/schedule-variance)
- [Project Baseline](https://learn.benibix.com/term/business/project-baseline)

## Told apart from

- [Planned Value vs Earned Value](https://learn.benibix.com/compare/planned-value-vs-earned-value): People think earned value is the money earned or the work planned. It is neither. Planned value is the budget for the work that should be done by now. Earned value is the budget for the work that is really done. The gap between them shows if the project is behind.

![Three lines rise over time against money. The planned value curve rises in an S shape to the total budget at the end. At a line marked today, the actual cost line sits above the earned value line, and both sit below planned value. The gap between earned value and planned value is marked schedule variance, and the gap between earned value and actual cost is marked cost variance. A dashed line runs on from actual cost to a point above the budget, marked estimate at completion.](https://learn.benibix.com/diagrams/pm-earned-value.svg)

---

Source: https://learn.benibix.com/term/business/planned-value
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.