# Project Baseline

> The plan that was agreed, then frozen. Progress is checked against it.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** Baseline, Performance Measurement Baseline

## Think of it like

It is like a photo of your room on the first day. Later you compare the room with the photo.

## Definition

A project baseline is the approved version of the plan, frozen at a point in time. It usually covers scope, schedule and cost. Progress is measured against it to see how far the project has drifted. It only changes through change control. Then the new version is saved, and the old one is kept for the record.

## Example

Lucy's baseline says the launch is on 3 March for 90,000 dollars. Now it looks like 17 March, so she is two weeks late.

## Why it matters

If the baseline keeps moving, the project always looks on plan. A fixed one shows the real drift.

## Common mistake

Quietly editing the baseline to hide a slip. That deletes the very thing it is for.

## Three principles

- **Approved.** Signed off, then frozen.
- **Three parts.** Scope, schedule and cost.
- **Changed formally.** Only through change control.

## Related terms

- [Change Control](https://learn.benibix.com/term/business/change-control)
- [Project Management Plan](https://learn.benibix.com/term/business/project-management-plan)
- [Planned Value (PV)](https://learn.benibix.com/term/business/planned-value)
- [Project Schedule](https://learn.benibix.com/term/business/project-schedule)
- [Project Budget](https://learn.benibix.com/term/business/project-budget)

## Told apart from

- [Project Baseline vs Project Schedule](https://learn.benibix.com/compare/project-baseline-vs-project-schedule): People think the baseline is just the current schedule. The schedule changes every week as work moves. The baseline is the plan as it was agreed, frozen. The gap between the two is how far the project has slipped.

![A flow of boxes. A change request goes to an impact check of time, cost and scope, then to the change control board. From the board, one arrow marked approved leads to update the baseline, and one marked rejected leads to tell the person who asked. Both outcomes are written in the change log.](https://learn.benibix.com/diagrams/pm-change-control.svg)

---

Source: https://learn.benibix.com/term/business/project-baseline
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.