# Schedule Variance (SV)

> Earned value take away planned value. Less than zero means you are late.

**Field:** Business & Startups  
**Category:** Scope, Schedule & Cost  
**Also known as:** SV

## Think of it like

It is like being on page 80 when your reading plan said page 100. You are 20 pages behind.

## Definition

Schedule variance shows whether a project is ahead of or behind its plan. You find it by taking planned value away from earned value. A negative number means less work is done than planned. A positive number means the team is ahead. It is given in money, not days.

## Formula

```
SV = EV - PV
```

## Example

Earned value is 30,000 dollars and planned value is 40,000. Schedule variance is minus 10,000 dollars, so the work is behind.

## Why it matters

It puts a size on lateness, so you can tell a small slip from a big one.

## Common mistake

Reading it as days. It is a money's worth of work, so turn it into time with care.

## Three principles

- **EV minus PV.** Work done against work planned.
- **The sign matters.** Negative is behind.
- **In money.** Not in days.

## Related terms

- [Schedule Performance Index (SPI)](https://learn.benibix.com/term/business/schedule-performance-index)
- [Cost Variance (CV)](https://learn.benibix.com/term/business/cost-variance)
- [Earned Value (EV)](https://learn.benibix.com/term/business/earned-value)
- [Planned Value (PV)](https://learn.benibix.com/term/business/planned-value)

![Three lines rise over time against money. The planned value curve rises in an S shape to the total budget at the end. At a line marked today, the actual cost line sits above the earned value line, and both sit below planned value. The gap between earned value and planned value is marked schedule variance, and the gap between earned value and actual cost is marked cost variance. A dashed line runs on from actual cost to a point above the budget, marked estimate at completion.](https://learn.benibix.com/diagrams/pm-earned-value.svg)

---

Source: https://learn.benibix.com/term/business/schedule-variance
Author: Behnia Zarei (a developer in Vienna, Austria, who builds and teaches data, AI and business intelligence at BENIBIX)
Publisher: BENIBIX Learn (https://learn.benibix.com/)
Last updated: 2026-11-19
Licence: CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Quote freely with attribution.