Project Baseline vs Project Schedule

People think the baseline is just the current schedule. The schedule changes every week as work moves. The baseline is the plan as it was agreed, frozen. The gap between the two is how far the project has slipped.

Business📅 Scope, Schedule & Cost

Project Baseline

The plan that was agreed, then frozen. Progress is checked against it.

A project baseline is the approved version of the plan, frozen at a point in time. It usually covers scope, schedule and cost. Progress is measured against it to see how far the project has drifted. It only changes through change control. Then the new version is saved, and the old one is kept for the record.

Example
Lucy's baseline says the launch is on 3 March for 90,000 dollars. Now it looks like 17 March, so she is two weeks late.
Why it matters
If the baseline keeps moving, the project always looks on plan. A fixed one shows the real drift.
Full entry
Business📅 Scope, Schedule & Cost

Project Schedule

The plan of when each task starts and ends. It also shows which tasks wait for others.

A project schedule lists every task with its start date and end date. It shows which tasks must wait for others. It shows the milestones the team must reach. It is built from the work breakdown structure and the time each task needs. Once agreed, it becomes the yardstick for whether the project is late.

Example
Emma's schedule has 60 tasks over five months. The shop opens in June if every task keeps its dates.
Why it matters
With no schedule, nobody knows the project is late. By the time they find out, it is too late to fix.
Full entry

In one line

Project Baseline
The plan that was agreed, then frozen. Progress is checked against it.
Project Schedule
The plan of when each task starts and ends. It also shows which tasks wait for others.