Project Schedule vs Gantt Chart

People think the Gantt chart is the schedule. The schedule is the plan itself: the tasks, how long they take, the order and the dates. A Gantt chart is one way to draw it, as bars on a timeline. The same schedule can also be a list or a network.

Business📅 Scope, Schedule & Cost

Project Schedule

The plan of when each task starts and ends. It also shows which tasks wait for others.

A project schedule lists every task with its start date and end date. It shows which tasks must wait for others. It shows the milestones the team must reach. It is built from the work breakdown structure and the time each task needs. Once agreed, it becomes the yardstick for whether the project is late.

Example
Emma's schedule has 60 tasks over five months. The shop opens in June if every task keeps its dates.
Why it matters
With no schedule, nobody knows the project is late. By the time they find out, it is too late to fix.
Full entry
Business📅 Scope, Schedule & Cost

Gantt Chart

A chart of task bars on a timeline. Each bar shows when one task starts and ends.

A Gantt chart shows a project's tasks as bars on a timeline. Each row is one task. Each bar starts on the task's start date and ends on its end date. Arrows between bars show which tasks wait for others. Diamonds mark the milestones. It is named after Henry Gantt, who made it popular in the 1910s.

Example
Lucy's Gantt chart shows the painting bar starting only after the walls bar ends.
Why it matters
One look shows what happens when, what overlaps and what is running late.
Full entry

In one line

Project Schedule
The plan of when each task starts and ends. It also shows which tasks wait for others.
Gantt Chart
A chart of task bars on a timeline. Each bar shows when one task starts and ends.