Contingency Plan vs Contingency Reserve

People think the contingency plan and the contingency reserve are one thing. The plan is the steps the team will take if a risk happens, such as calling the backup hotel. The reserve is the money set aside to pay for steps like that. A risk can have a plan and draw on the reserve, or have one without the other.

Business⚠️ Risk, Quality & Procurement

Contingency Plan

A plan made ahead of time. It is used only if the risk comes true.

A contingency plan says what the team will do if a risk happens. It is written ahead of time but only used when a trigger fires. It names the steps, the owner and the money or time it may need. Until then, nothing in it is done. It turns a crisis into steps everyone already knows.

Example
Jack's event is in Dubai. If the main venue cancels, his plan says to call the backup hotel within an hour.
Why it matters
Choices made in a panic are often bad. A plan written in calm lets the team act fast and well.
Full entry
Business📅 Scope, Schedule & Cost

Contingency Reserve

Money or time kept aside for the risks the team has found.

A contingency reserve is money or time set aside for risks you have already spotted. These are called known unknowns: you know they might happen, but not if they will. The reserve is sized from the risk list. It is part of the cost baseline, and the project manager can use it as each risk comes true. Leftover reserve can be given back.

Example
A team thinks rain may stop building for a week. They add 5 days and 12,000 dollars to cover it.
Why it matters
Known risks will cost something if they happen. Planning for them stops one bad week from sinking the budget.
Full entry

In one line

Contingency Plan
A plan made ahead of time. It is used only if the risk comes true.
Contingency Reserve
Money or time kept aside for the risks the team has found.