Contingency Reserve

Business📅 Scope, Schedule & CostProject Cost

Also known as Contingency, Risk Reserve

Money or time kept aside for the risks the team has found.

Think of it like

It is like packing a coat when the sky says it might rain. You know the risk, so you plan for it.

Example

A team thinks rain may stop building for a week. They add 5 days and 12,000 dollars to cover it.

Why it matters

Known risks will cost something if they happen. Planning for them stops one bad week from sinking the budget.

Definition

A contingency reserve is money or time set aside for risks you have already spotted. These are called known unknowns: you know they might happen, but not if they will. The reserve is sized from the risk list. It is part of the cost baseline, and the project manager can use it as each risk comes true. Leftover reserve can be given back.
This reserve sits right on top of the cost of the work. It is inside the cost baseline.

Common mistake

Using it to cover mistakes or new work. It is only for the risks it was set aside for.

Key takeaways

  1. 1
    Known risks. Sized from the risk list.
  2. 2
    Inside the baseline. Part of the planned cost.
  3. 3
    Manager's call. The project manager can use it.