Earned Value vs Actual Cost

People think earned value is the money spent so far. Actual cost is the money spent. Earned value is what the finished work was planned to cost. When actual cost is higher than earned value, the work is costing more than it should.

Business📅 Scope, Schedule & Cost

Earned Value (EV)

The budget for the work that is really done so far.

Earned value is the budget for the work that is actually finished. You find it by multiplying the share of work done by the total budget. If a 100,000 dollar project is 30% done, its earned value is 30,000 dollars. It does not care what was spent. It only measures what was achieved.

Example
A 100,000 dollar project is 30% done. Its earned value is 30,000 dollars, whatever was spent.
Formula
EV = % of work complete x BAC, the budget for all the work
Why it matters
It turns progress into money, so it can be compared with both the plan and the spend.
Full entry
Business📅 Scope, Schedule & Cost

Actual Cost (AC)

The money really spent on the work done so far.

Actual cost is the money really spent on the work done so far. It comes from invoices, timesheets and bills. It is compared with earned value to see if the work cost more than planned. If the work done was worth 30,000 dollars but cost 36,000, the project is over budget.

Example
Timesheets and bills for March add up to 36,000 dollars. That is the actual cost to date.
Why it matters
On its own it means little. Next to earned value it shows if money is being well spent.
Full entry

In one line

Earned Value (EV)
The budget for the work that is really done so far.
Actual Cost (AC)
The money really spent on the work done so far.