📅Earned Value (EV)
Also known as EV, Budgeted Cost of Work Performed, BCWP
The budget for the work that is really done so far.
Think of it like
It is like counting the pages you have really read. It does not matter how long it took.
Example
A 100,000 dollar project is 30% done. Its earned value is 30,000 dollars, whatever was spent.
Why it matters
It turns progress into money, so it can be compared with both the plan and the spend.
Formula
EV = % of work complete x BAC, the budget for all the workDefinition
Common mistake
Key takeaways
- 1Work done. Only finished work counts.
- 2Planned price. Valued at its budget, not its cost.
- 3The middle number. Compared with plan and spend.