Change Request

Business📅 Scope, Schedule & CostChange Control

Also known as Project Change Request

A written ask to change what was agreed. It might be the scope, the dates or the cost.

Think of it like

It is like a note to your teacher asking to swap your project topic. It says what and why.

Example

Emma sends a change request to add live chat. It adds 3 weeks and 15,000 euros, and the board says yes.

Why it matters

It turns a remark in a hallway into a real choice. It can be priced, decided and tracked.

Definition

A change request is a formal ask to change something agreed in the project. It might add work, move a date, raise a cost or fix a defect. It says what should change, why, and what it will affect. It then goes through change control to be approved or turned down. Every request is logged, even the ones that are refused.
The change request is the first box. Nothing moves until it is written down.

Common mistake

Starting the work before the request is approved. If it is turned down, that work is wasted.

Key takeaways

  1. 1
    Written. A word in passing does not count.
  2. 2
    Costed. Shows the effect on time and money.
  3. 3
    Logged. Kept, whether the answer is yes or no.