Scope, Schedule & Cost

Saying what the work is, when it lands, what it costs, and controlling every change to any of it · 44 terms

Sort
Compare

Project Scope

9

What a project will make and leave out, how the work is broken into pieces, and how the scope is defined and kept in check.

All the work a project will do. It also says what is left out.

A tree that splits a project's work into small pieces. Each piece can be planned.

The smallest box in a work breakdown structure. It can be costed, timed and owned.

Scope Definition

4

The papers and tables that pin the scope down: what is needed, what will be handed over and how each need is traced.

A written page that says what a project will make, and what it will not.

The needs a project's result must meet. Each one is written down and checked.

A table that links each need to the work and the test that meet it.

A thing a project must make and hand over. It can be checked and accepted.

Scope Control

2

The ways extra work slips into a project without approval.

Extra work that creeps into a project. It comes one small ask at a time.

Extras the team adds on its own. Nobody asked for them or approved them.

Project Schedule

18

When the work happens: the schedule and how it is drawn, how long tasks will take, which tasks set the end date, and how to finish sooner.

The plan of when each task starts and ends. It also shows which tasks wait for others.

A key moment in a project, like a sign-off. It takes no time itself.

A chart of task bars on a timeline. Each bar shows when one task starts and ends.

Plan the next few weeks in detail. Leave later work rough until it gets close.

A best guess of how long work will take or what it will cost.

A way to plan dates using three guesses for each task, blended into one.

A way to find the longest chain of tasks in a project. That chain sets the end date.

Ways to finish a project sooner. The scope stays the same.

Doing tasks at the same time. Usually they would go one after the other.

Adding people or money to the key tasks. Then they finish sooner.

Moving tasks so no one has too much work on one day.

Estimation Techniques

3

Ways to put a number on how long work will take or what it will cost, from quick and rough to slow and exact.

An estimate made from three guesses. They are the best case, the most likely and the worst.

Estimate each small piece of work. Then add them all up for the total.

A fast guess. It copies the time or cost of a past project like this one.

Schedule Network

4

The links between tasks, the waits on them, and the chain that decides when the project can end.

A link between two tasks. One task must wait for the other.

A planned wait or head start on the link between two tasks.

The longest chain of tasks in a project. A delay on it delays the end.

How long a task can slip before it makes the project late.

Project Cost

13

The money: the budget and its cushions for risk, and how earned value tracks cost and progress together.

All the money set aside for a project. It has a cushion for risk.

Money or time kept aside for the risks the team has found.

Money kept for surprises no one could plan for. Bosses must say yes to use it.

A way to track a project's time and cost. It compares three numbers.

Earned Value Metrics

9

The numbers earned value management is built from, and the forecast it makes from them.

The budget for the work that should be done by now. It comes from the plan.

The budget for the work that is really done so far.

The money really spent on the work done so far.

The total budget for all the planned work. It is where the plan ends up.

A guess of what the whole project will cost by the end.

Variances2

Gaps in money between the work done and the plan or the spend. Below zero is bad news.

Earned value take away planned value. Less than zero means you are late.

Earned value take away actual cost. Less than zero means you spent too much.

Performance Indexes2

Ratios of the work done to the plan or the spend. A low score means behind or over budget.

Earned value divided by planned value. Under 1 means the work is behind.

Earned value divided by actual cost. Under 1 means the work costs too much.

Change Control

4

How a change to an agreed plan is asked for, weighed, decided and recorded, and the frozen plan it is measured against.

The way a team checks and agrees to changes in its plan.

The plan that was agreed, then frozen. Progress is checked against it.

A written ask to change what was agreed. It might be the scope, the dates or the cost.

The group that looks at each change request. It says yes or no.