Net Present Value (NPV)

Business🏦 Corporate FinanceCapital Budgeting

Also known as NPV

Future cash brought back to today's value, minus the cost. Above zero means go.

Think of it like

Shrink each future coin to what it is worth today. Add them up. Take away what you paid.

Example

A $250 machine will save Jack $100 a year for three years. At 10%, those savings are worth $249 today, so the NPV is minus $1.

Why it matters

It counts every dollar, its timing and its risk in one number. Finance teams trust it more than ROI or payback.

Formula

NPV = Sum of (Cash in Year t ÷ (1 + Rate) ^ t) - Cost

Definition

Net present value tells you if a project is worth more than it costs, in today's money. You shrink each future cash flow back to today using a discount rate. Then you add them all up and subtract the cost. A positive NPV means the project adds value. A negative NPV means the money would do better elsewhere. It is the standard test for big spending choices.
The three payments are worth $249 today. If the project costs $200, its NPV is $49.

Common mistake

Trusting it more than its inputs. A guessed cash flow or the wrong discount rate gives a confident wrong answer.

Key takeaways

  1. 1
    Bring cash to today. Shrink each year's cash.
  2. 2
    Subtract the cost. What is left is the value added.
  3. 3
    Above zero, go. Below zero, the money fits elsewhere.