Planning Fallacy

General🧠 PsychologyCognitive Biases

Also known as Planning Bias

Guessing a job will be quick, even when past jobs ran late.

Think of it like

It is like saying you will tidy your room in ten minutes. It takes an hour, every time.

Example

A team says the new website will be ready in a month. Their last three sites each took three months, and this one does too.

Why it matters

Late plans cost money and trust. Knowing the bias lets you add time before the deadline is set, not after.

Definition

The planning fallacy is guessing that a job will take less time, money or effort than it really will. We picture the plan going well and forget what went wrong last time. Daniel Kahneman and Amos Tversky named it in 1979. In a 1994 study, students guessed their final paper would take about 34 days. It took about 56 days on average.
Left: students guessed about 34 days for their paper, and it took about 56.

Common mistake

Trying to fix it by planning in more detail. More steps on paper still feel smooth. Look at how long past jobs like this one really took.

Key takeaways

  1. 1
    Best case feels likely. We picture the plan going right.
  2. 2
    Past jobs are a guide. Check how long similar jobs took.
  3. 3
    Add a buffer. Plan extra time before you start.