Three-Point Estimate

Business📅 Scope, Schedule & CostProject Schedule

Also known as PERT Estimate, Three-Point Estimating

An estimate made from three guesses. They are the best case, the most likely and the worst.

Think of it like

It is like guessing your walk to school. On a good day it takes 10 minutes, on a bad day 20, and most days 12.

Example

A task could take 4 days at best, 6 most likely or 14 at worst. The blend gives (4 + 24 + 14) / 6 = 7 days.

Why it matters

One number hides the risk. Three numbers show it, and a long worst case pulls the answer up.

Formula

Estimate = (O + 4M + P) / 6, where O is the best case, M the most likely and P the worst case

Definition

A three-point estimate uses three guesses instead of one. The first is the best case, the second is the most likely and the third is the worst case. These are then blended into one number. The common blend gives the most likely guess four times the weight of the others. The gap between best and worst also shows how unsure the guess is.
The worst case is far out to the right. It pulls the blend past the most likely day.

Common mistake

Picking a worst case that is still hopeful. The worst case should be truly bad, but possible.

Key takeaways

  1. 1
    Three guesses. Best, most likely and worst.
  2. 2
    Weighted. The most likely counts four times.
  3. 3
    Shows doubt. A wide gap means high risk.