BAC vs EAC
People think the EAC is just the budget. It is not. The BAC is the budget, the total of the plan, and it stays fixed. The EAC is today's guess of what the whole project will cost. It moves with every report.
Budget at Completion (BAC)
The total budget for all the planned work. It is where the plan ends up.
Budget at completion, or BAC, is the total budget for all the planned work on a project. It is the top of the planned value line, reached on the last day. If a project plans to spend 100,000 dollars on its work, its BAC is 100,000 dollars. It leaves out the management reserve. It only changes when an approved change moves the plan.
Estimate at Completion (EAC)
A guess of what the whole project will cost by the end.
Estimate at completion is the forecast of what the whole project will cost when it is done. The common way divides the total budget by the cost performance index. This assumes the project keeps spending at today's rate. If a 100,000 dollar project has an index of 0.83, it will cost about 120,000. Other formulas assume the rest of the work goes to plan.
EAC = BAC / CPI, where BAC (budget at completion) is the budget for all the workIn one line