People think the EAC is just the budget. It is not. The BAC is the budget, the total of the plan, and it stays fixed. The EAC is today's guess of what the whole project will cost. It moves with every report.

Business📅 Scope, Schedule & Cost

Budget at Completion (BAC)

The total budget for all the planned work. It is where the plan ends up.

Budget at completion, or BAC, is the total budget for all the planned work on a project. It is the top of the planned value line, reached on the last day. If a project plans to spend 100,000 dollars on its work, its BAC is 100,000 dollars. It leaves out the management reserve. It only changes when an approved change moves the plan.

Example
Lucy's office move has a BAC of 120,000 dollars. Halfway through, her forecast says 132,000, so she is heading 12,000 over.
Why it matters
Each guess of the final cost starts from it. With no fixed total, there is nothing to hold an overrun up to.
Full entry
Business📅 Scope, Schedule & Cost

Estimate at Completion (EAC)

A guess of what the whole project will cost by the end.

Estimate at completion is the forecast of what the whole project will cost when it is done. The common way divides the total budget by the cost performance index. This assumes the project keeps spending at today's rate. If a 100,000 dollar project has an index of 0.83, it will cost about 120,000. Other formulas assume the rest of the work goes to plan.

Example
The budget is 100,000 dollars and the index is 0.83. The forecast is 100,000 / 0.83, about 120,000 dollars.
Formula
EAC = BAC / CPI, where BAC (budget at completion) is the budget for all the work
Why it matters
It tells leaders early how much more money to find. They learn it before the money runs out.
Full entry

In one line

Budget at Completion (BAC)
The total budget for all the planned work. It is where the plan ends up.
Estimate at Completion (EAC)
A guess of what the whole project will cost by the end.