Estimate at Completion (EAC)

Business📅 Scope, Schedule & CostProject Cost

Also known as EAC

A guess of what the whole project will cost by the end.

Think of it like

It is like spending half your pocket money in one week. You can guess it will run out before the month ends.

Example

The budget is 100,000 dollars and the index is 0.83. The forecast is 100,000 / 0.83, about 120,000 dollars.

Why it matters

It tells leaders early how much more money to find. They learn it before the money runs out.

Formula

EAC = BAC / CPI, where BAC (budget at completion) is the budget for all the work

Definition

Estimate at completion is the forecast of what the whole project will cost when it is done. The common way divides the total budget by the cost performance index. This assumes the project keeps spending at today's rate. If a 100,000 dollar project has an index of 0.83, it will cost about 120,000. Other formulas assume the rest of the work goes to plan.
The dashed line carries today's spending rate to the end. It lands above the budget.

Common mistake

Keeping the original budget as the forecast. If the index is below 1, the end cost will be higher.

Key takeaways

  1. 1
    Forecast. The likely final cost.
  2. 2
    Today's rate. The common formula assumes it holds.
  3. 3
    Update it. Work it out again at every report.