Budget at Completion (BAC)

Business📅 Scope, Schedule & CostProject Cost

Also known as BAC

The total budget for all the planned work. It is where the plan ends up.

Think of it like

It is like the price on the ticket before a trip. It is what you plan to pay in all.

Example

Lucy's office move has a BAC of 120,000 dollars. Halfway through, her forecast says 132,000, so she is heading 12,000 over.

Why it matters

Each guess of the final cost starts from it. With no fixed total, there is nothing to hold an overrun up to.

Definition

Budget at completion, or BAC, is the total budget for all the planned work on a project. It is the top of the planned value line, reached on the last day. If a project plans to spend 100,000 dollars on its work, its BAC is 100,000 dollars. It leaves out the management reserve. It only changes when an approved change moves the plan.
The planned value line ends at the total budget. That top point is the budget at completion.

Common mistake

Adding the management reserve to it. That money sits outside the plan. The project then looks on budget while it eats the reserve.

Key takeaways

  1. 1
    The whole plan. All the planned work, added up.
  2. 2
    Fixed. It changes only through an approved change.
  3. 3
    Start of the forecast. The final cost forecast divides it by the CPI.