Burndown Chart vs Burnup Chart

People think the two charts show the same thing. A burndown counts work left and falls to zero. A burnup counts work done and climbs to a scope line. Only the burnup shows when work is added, so a flat burndown can hide a team that is working hard.

Business📋 Agile Delivery

Burndown Chart

A chart of work left over time. It should slope down to zero by the end.

A burndown chart shows how much work is left over time. The up axis is work left, in points or tasks. The bottom axis is the days of a sprint, or the sprints of a release. A straight ideal line runs from the start total down to zero. The real line shows what is truly left each day. If it sits above the ideal line, the team is behind.

Example
Lucy's sprint starts with 40 points. On day 6 the chart shows 24 points left, above the ideal line at 16, so the team talks it through at the daily scrum.
Why it matters
It shows trouble early, while there is still time to act. A flat line for days means the team is stuck.
Full entry
Business📋 Agile Delivery

Burnup Chart

A chart of work done climbing toward a scope line. It shows when scope changes.

A burnup chart shows work done rising over time. It has two lines. One climbs as work is finished. The other shows the total scope. When the two lines meet, the work is done. Because scope has its own line, you can see when work is added or taken away.

Example
A release starts at 60 points and grows to 80 in sprint 4. The done line climbs 10 points a sprint and meets the scope line in sprint 8.
Why it matters
It splits two things a burndown mixes up: the team is slow, or the work grew. Stakeholders see why a date moved.
Full entry

In one line

Burndown Chart
A chart of work left over time. It should slope down to zero by the end.
Burnup Chart
A chart of work done climbing toward a scope line. It shows when scope changes.