Burnup Chart

Business📋 Agile DeliveryPlanning

Also known as Burn-Up Chart, Release Burnup

A chart of work done climbing toward a scope line. It shows when scope changes.

Think of it like

It is like climbing to a flag on a hill. If someone moves the flag higher, you can see it.

Example

A release starts at 60 points and grows to 80 in sprint 4. The done line climbs 10 points a sprint and meets the scope line in sprint 8.

Why it matters

It splits two things a burndown mixes up: the team is slow, or the work grew. Stakeholders see why a date moved.

Definition

A burnup chart shows work done rising over time. It has two lines. One climbs as work is finished. The other shows the total scope. When the two lines meet, the work is done. Because scope has its own line, you can see when work is added or taken away.
The scope line jumped in sprint 4. The done line kept its pace, so the finish moved out, and everyone can see why.

Common mistake

Drawing it without the scope line. Then it only counts work done and hides the very thing it is for.

Key takeaways

  1. 1
    Two lines. One for work done, one for scope.
  2. 2
    Scope is in view. Added work shows as a jump.
  3. 3
    Done where they meet. The finish is where the lines touch.