Burndown Chart

Business📋 Agile DeliveryPlanning

Also known as Burn-Down Chart, Sprint Burndown

A chart of work left over time. It should slope down to zero by the end.

Think of it like

It is like a candle burning down through the evening. You can see how much is left and guess when it will run out.

Example

Lucy's sprint starts with 40 points. On day 6 the chart shows 24 points left, above the ideal line at 16, so the team talks it through at the daily scrum.

Why it matters

It shows trouble early, while there is still time to act. A flat line for days means the team is stuck.

Definition

A burndown chart shows how much work is left over time. The up axis is work left, in points or tasks. The bottom axis is the days of a sprint, or the sprints of a release. A straight ideal line runs from the start total down to zero. The real line shows what is truly left each day. If it sits above the ideal line, the team is behind.
The dashed line is the ideal pace. The real line stalled for two days, then caught up by the last day.

Common mistake

Hiding work that was added. When scope grows, the line can look flat even while the team works hard. A burnup chart shows that better.

Key takeaways

  1. 1
    Work left over time. Points left up the side, days along the bottom.
  2. 2
    Ideal line as a guide. Above it means behind, below means ahead.
  3. 3
    Flat means stuck. No drop for days needs a talk.