Contingency Reserve vs Management Reserve
People think the two reserves are one pot of spare money. One is for risks the team has listed, and the project manager can spend it. It sits inside the cost baseline. The other is for surprises no one could list. It sits outside the baseline, and a leader must say yes before it is used.
Contingency Reserve
Money or time kept aside for the risks the team has found.
A contingency reserve is money or time set aside for risks you have already spotted. These are called known unknowns: you know they might happen, but not if they will. The reserve is sized from the risk list. It is part of the cost baseline, and the project manager can use it as each risk comes true. Leftover reserve can be given back.
Management Reserve
Money kept for surprises no one could plan for. Bosses must say yes to use it.
A management reserve is money set aside for problems no one could see coming. People call these unknown unknowns. It sits outside the cost baseline, but inside the total budget. The project manager cannot spend it alone. A sponsor or a senior boss must approve each use. Then the baseline is changed to match.
In one line
- Contingency Reserve
- Money or time kept aside for the risks the team has found.
- Management Reserve
- Money kept for surprises no one could plan for. Bosses must say yes to use it.