Management Reserve

Business📅 Scope, Schedule & CostProject Cost

Money kept for surprises no one could plan for. Bosses must say yes to use it.

Think of it like

It is like the spare cash your mum keeps in a jar. It is for things no one saw coming.

Example

A supplier goes out of business halfway through. The sponsor releases 20,000 pounds from the management reserve.

Why it matters

Some shocks cannot be listed in advance. This cushion keeps them from stopping the project.

Definition

A management reserve is money set aside for problems no one could see coming. People call these unknown unknowns. It sits outside the cost baseline, but inside the total budget. The project manager cannot spend it alone. A sponsor or a senior boss must approve each use. Then the baseline is changed to match.
The management reserve sits on top, outside the cost baseline. Using it needs a leader's yes.

Common mistake

Counting it in the cost baseline. Then the project looks on budget while it quietly eats the reserve.

Key takeaways

  1. 1
    Unknown risks. For what no one could list.
  2. 2
    Outside the baseline. Not part of the planned cost.
  3. 3
    Needs approval. Leaders decide when it is used.