Planned Value vs Earned Value

People think earned value is the money earned or the work planned. It is neither. Planned value is the budget for the work that should be done by now. Earned value is the budget for the work that is really done. The gap between them shows if the project is behind.

Business📅 Scope, Schedule & Cost

Planned Value (PV)

The budget for the work that should be done by now. It comes from the plan.

Planned value is the budget for the work that should be done by a given date. You read it straight from the plan. If a 100,000 dollar project planned 40% of its work by month three, planned value is 40,000 dollars. Over the whole project it climbs to the full budget. It is the line every other number is compared with.

Example
A 200,000 dollar build planned to be half done by June. Its planned value in June is 100,000 dollars.
Why it matters
Without it, "how far along are we?" has nothing to be compared with.
Full entry
Business📅 Scope, Schedule & Cost

Earned Value (EV)

The budget for the work that is really done so far.

Earned value is the budget for the work that is actually finished. You find it by multiplying the share of work done by the total budget. If a 100,000 dollar project is 30% done, its earned value is 30,000 dollars. It does not care what was spent. It only measures what was achieved.

Example
A 100,000 dollar project is 30% done. Its earned value is 30,000 dollars, whatever was spent.
Formula
EV = % of work complete x BAC, the budget for all the work
Why it matters
It turns progress into money, so it can be compared with both the plan and the spend.
Full entry

In one line

Planned Value (PV)
The budget for the work that should be done by now. It comes from the plan.
Earned Value (EV)
The budget for the work that is really done so far.