Planned Value vs Earned Value
People think earned value is the money earned or the work planned. It is neither. Planned value is the budget for the work that should be done by now. Earned value is the budget for the work that is really done. The gap between them shows if the project is behind.
Planned Value (PV)
The budget for the work that should be done by now. It comes from the plan.
Planned value is the budget for the work that should be done by a given date. You read it straight from the plan. If a 100,000 dollar project planned 40% of its work by month three, planned value is 40,000 dollars. Over the whole project it climbs to the full budget. It is the line every other number is compared with.
Earned Value (EV)
The budget for the work that is really done so far.
Earned value is the budget for the work that is actually finished. You find it by multiplying the share of work done by the total budget. If a 100,000 dollar project is 30% done, its earned value is 30,000 dollars. It does not care what was spent. It only measures what was achieved.
EV = % of work complete x BAC, the budget for all the workIn one line
- Planned Value (PV)
- The budget for the work that should be done by now. It comes from the plan.
- Earned Value (EV)
- The budget for the work that is really done so far.