📅Planned Value (PV)
Also known as PV, Budgeted Cost of Work Scheduled, BCWS
The budget for the work that should be done by now. It comes from the plan.
Think of it like
It is like a plan that says you should read up to page 100 by Friday.
Example
A 200,000 dollar build planned to be half done by June. Its planned value in June is 100,000 dollars.
Why it matters
Without it, "how far along are we?" has nothing to be compared with.
Definition
Common mistake
Key takeaways
- 1From the plan. Read off the schedule and budget.
- 2Grows over time. Climbs to the full budget.
- 3The yardstick. Earned value is checked against it.