Planned Value (PV)

Business📅 Scope, Schedule & CostProject Cost

Also known as PV, Budgeted Cost of Work Scheduled, BCWS

The budget for the work that should be done by now. It comes from the plan.

Think of it like

It is like a plan that says you should read up to page 100 by Friday.

Example

A 200,000 dollar build planned to be half done by June. Its planned value in June is 100,000 dollars.

Why it matters

Without it, "how far along are we?" has nothing to be compared with.

Definition

Planned value is the budget for the work that should be done by a given date. You read it straight from the plan. If a 100,000 dollar project planned 40% of its work by month three, planned value is 40,000 dollars. Over the whole project it climbs to the full budget. It is the line every other number is compared with.
Planned value is the S-shaped curve. It shows how much work should be done by each date.

Common mistake

Mixing it up with money spent. Planned value is what the plan said, not what was paid.

Key takeaways

  1. 1
    From the plan. Read off the schedule and budget.
  2. 2
    Grows over time. Climbs to the full budget.
  3. 3
    The yardstick. Earned value is checked against it.