Skip to content
BENIBIX Learn

Three-Point Estimate vs PERT

People think a three-point estimate and PERT are the same thing. A three-point estimate blends three guesses for one task. PERT is a whole way to plan the dates, built on one blend of those guesses. You can use the first without the second.

Business📅 Scope, Schedule & Cost

Three-Point Estimate

An estimate made from three guesses. They are the best case, the most likely and the worst.

A three-point estimate uses three guesses instead of one. The first is the best case, the second is the most likely and the third is the worst case. These are then blended into one number. The common blend gives the most likely guess four times the weight of the others. The gap between best and worst also shows how unsure the guess is.

Example
A task could take 4 days at best, 6 most likely or 14 at worst. The blend gives (4 + 24 + 14) / 6 = 7 days.
Formula
Estimate = (O + 4M + P) / 6, where O is the best case, M the most likely and P the worst case
Why it matters
One number hides the risk. Three numbers show it, and a long worst case pulls the answer up.
Full entry
Business📅 Scope, Schedule & Cost

Program Evaluation and Review Technique (PERT)

A way to plan dates using three guesses for each task, blended into one.

PERT is a way to plan a project's dates when task times are unsure. The name is short for Program Evaluation and Review Technique. Each task gets three guesses: best, most likely and worst. They are blended with one sum: best, plus four times likely, plus worst, divided by 6. The blended times are then joined into a chain to find the end date. It was built for the US Navy in the late 1950s.

Example
A task could take 4, 6 or 14 days. PERT blends them into (4 + 24 + 14) / 6 = 7 days, and that 7 goes into the schedule.
Why it matters
It shows that tasks run late more often than early. A plan built on PERT times is late less often than one built on hopeful times.
Full entry

In one line

Three-Point Estimate
An estimate made from three guesses. They are the best case, the most likely and the worst.
Program Evaluation and Review Technique (PERT)
A way to plan dates using three guesses for each task, blended into one.