Three-Point Estimate vs PERT
People think a three-point estimate and PERT are the same thing. A three-point estimate blends three guesses for one task. PERT is a whole way to plan the dates, built on one blend of those guesses. You can use the first without the second.
Three-Point Estimate
An estimate made from three guesses. They are the best case, the most likely and the worst.
A three-point estimate uses three guesses instead of one. The first is the best case, the second is the most likely and the third is the worst case. These are then blended into one number. The common blend gives the most likely guess four times the weight of the others. The gap between best and worst also shows how unsure the guess is.
Estimate = (O + 4M + P) / 6, where O is the best case, M the most likely and P the worst caseProgram Evaluation and Review Technique (PERT)
A way to plan dates using three guesses for each task, blended into one.
PERT is a way to plan a project's dates when task times are unsure. The name is short for Program Evaluation and Review Technique. Each task gets three guesses: best, most likely and worst. They are blended with one sum: best, plus four times likely, plus worst, divided by 6. The blended times are then joined into a chain to find the end date. It was built for the US Navy in the late 1950s.
In one line
- Three-Point Estimate
- An estimate made from three guesses. They are the best case, the most likely and the worst.
- Program Evaluation and Review Technique (PERT)
- A way to plan dates using three guesses for each task, blended into one.