📅Program Evaluation and Review Technique (PERT)
Also known as PERT, PERT Chart, PERT Method
A way to plan dates using three guesses for each task, blended into one.
Think of it like
It is like asking three friends how long the drive will take. One is hopeful, one is fair and one expects jams.
Example
A task could take 4, 6 or 14 days. PERT blends them into (4 + 24 + 14) / 6 = 7 days, and that 7 goes into the schedule.
Why it matters
It shows that tasks run late more often than early. A plan built on PERT times is late less often than one built on hopeful times.
Definition
Common mistake
Key takeaways
- 1Three guesses. Best, most likely and worst for every task.
- 2Weighted blend. The most likely guess counts four times.
- 3Unsure times. It plans for tasks whose length is not known.