Program Evaluation and Review Technique (PERT)

Business📅 Scope, Schedule & CostProject Schedule

Also known as PERT, PERT Chart, PERT Method

A way to plan dates using three guesses for each task, blended into one.

Think of it like

It is like asking three friends how long the drive will take. One is hopeful, one is fair and one expects jams.

Example

A task could take 4, 6 or 14 days. PERT blends them into (4 + 24 + 14) / 6 = 7 days, and that 7 goes into the schedule.

Why it matters

It shows that tasks run late more often than early. A plan built on PERT times is late less often than one built on hopeful times.

Definition

PERT is a way to plan a project's dates when task times are unsure. The name is short for Program Evaluation and Review Technique. Each task gets three guesses: best, most likely and worst. They are blended with one sum: best, plus four times likely, plus worst, divided by 6. The blended times are then joined into a chain to find the end date. It was built for the US Navy in the late 1950s.
PERT blends three guesses into one. The long tail on the late side pulls the blend past the most likely day.

Common mistake

Thinking PERT and CPM are rivals. They work well together: PERT blends the guesses, and the critical path is then found the same way.

Key takeaways

  1. 1
    Three guesses. Best, most likely and worst for every task.
  2. 2
    Weighted blend. The most likely guess counts four times.
  3. 3
    Unsure times. It plans for tasks whose length is not known.