Crashing

Business📅 Scope, Schedule & CostProject Schedule

Also known as Project Crashing, Schedule Crashing

Adding people or money to the key tasks. Then they finish sooner.

Think of it like

It is like asking friends to help you clean your room. It goes faster, but you owe them a treat.

Example

A team pays for weekend shifts on the build task. It ends 5 days sooner and costs 8,000 euros more.

Why it matters

It buys time with money, when the date matters more than the budget.

Definition

Crashing shortens a schedule by adding people, money or tools to tasks on the critical path. It keeps the order of the tasks the same. Each day saved costs extra, so you crash the cheapest tasks first. At some point more people stop helping and only add cost. It works best on tasks that can be split between many hands.
Crashing is the bottom row. The order stays the same, and extra people make the build bar shorter.

Common mistake

Adding people late to work that cannot be split. New people need training and can slow the team down.

Key takeaways

  1. 1
    Pay for time. Each day saved costs more.
  2. 2
    Cheapest first. Crash the least costly task.
  3. 3
    Critical path only. Other tasks gain nothing.