📅Critical Path
The longest chain of tasks in a project. A delay on it delays the end.
Think of it like
It is like a line of dominoes. If one falls late, the last one falls late too.
Example
Design, build and test take 40 days in a row. The other tasks finish sooner, so these three are the critical path.
Why it matters
It shows where a day lost is a day lost for good. Tasks off the path have room to slip.
Definition
Common mistake
Key takeaways
- 1Longest chain. Its length is the end date.
- 2Zero float. No task on it can slip.
- 3It moves. A late task elsewhere can join it.