Critical Path

Business📅 Scope, Schedule & CostProject Schedule

The longest chain of tasks in a project. A delay on it delays the end.

Think of it like

It is like a line of dominoes. If one falls late, the last one falls late too.

Example

Design, build and test take 40 days in a row. The other tasks finish sooner, so these three are the critical path.

Why it matters

It shows where a day lost is a day lost for good. Tasks off the path have room to slip.

Definition

The critical path is the longest chain of linked tasks in a project. Its length is the shortest time the whole project can take. Each task on it has zero float, so it has no spare time. If one of them is a day late, the project ends a day late. A project can have more than one critical path.
The accent path is the critical path. A day lost on design, build or test is a day lost at the end.

Common mistake

Thinking the critical path is the most important work. It is the longest chain, not the most valuable.

Key takeaways

  1. 1
    Longest chain. Its length is the end date.
  2. 2
    Zero float. No task on it can slip.
  3. 3
    It moves. A late task elsewhere can join it.