Lead and Lag

Business📅 Scope, Schedule & CostProject Schedule

Also known as Lag, Lag Time

A planned wait or head start on the link between two tasks.

Think of it like

It is like baking a cake. You wait for it to cool before the icing goes on. But you can mix the icing while it bakes.

Example

New concrete needs 7 days to set before the walls go up. That is a lag of 7 days on the link.

Why it matters

They make the schedule match real life, with no fake tasks just for waiting.

Definition

Lead and lag change the timing of a link between two tasks. A lag is a planned wait: the next task starts some days after the first one ends. A lead is a head start: the next task begins before the first one ends. Both are written in days on the link. Neither is a task, so neither uses any work.
A lag adds a wait to the link. A lead lets the next task start a few days early.

Common mistake

Hiding a real task inside a lag. If someone does work in that gap, it should be its own task.

Key takeaways

  1. 1
    Lag. A planned wait after a task.
  2. 2
    Lead. A planned overlap before it ends.
  3. 3
    On the link. Not a task, and no work.