A way to find the longest chain of tasks in a project. That chain sets the end date.

Think of it like

It is like getting ready for school. Some jobs wait for others. The longest chain says when you leave.

Example

A website has 20 tasks. CPM shows that design, build and test form the longest chain, at 40 days.

Why it matters

It tells you which tasks can slip and which cannot. That is where to spend your attention.

Definition

The critical path method, or CPM, works out the shortest time a project can take. You list each task, how long it takes and what it must wait for. Then you find every chain of tasks from start to end. The longest chain is the critical path. CPM also shows how much spare time every other task has. It was first worked out in the late 1950s.
CPM adds up every chain from start to end. The longest one, 10 days, is the critical path.

Common mistake

Running it once at the start. The critical path moves as tasks finish early or late.

Key takeaways

  1. 1
    Longest chain. It sets the shortest finish.
  2. 2
    Spare time. Every other task gets its float.
  3. 3
    Run it again. The path changes as work moves.