Work Breakdown Structure (WBS)

Business📅 Scope, Schedule & CostProject Scope

Also known as WBS

A tree that splits a project's work into small pieces. Each piece can be planned.

Think of it like

It is like cutting a big pizza into slices. Each slice is small enough to eat.

Example

A wedding is split into venue, food and music. Food is split again into menu, tasting and serving.

Why it matters

You cannot plan or price a project as one lump. Small pieces can be costed, timed and handed to people.

Definition

A work breakdown structure, or WBS, splits a project's work into smaller pieces. It is drawn as a tree. The whole project sits at the top. Each level below splits the work into smaller parts. The lowest boxes are called work packages. All the pieces must add up to all the work, and nothing extra.
The project at the top, its parts below, and the work packages at the bottom.

Common mistake

Filling it with tasks in time order. It lists the pieces of the result, not the steps.

Key takeaways

  1. 1
    The 100% rule. The pieces add up to all the work.
  2. 2
    Results, not steps. Each box names a thing, not a task.
  3. 3
    Small at the bottom. The lowest boxes can be costed and timed.