Work Package

Business📅 Scope, Schedule & CostProject Scope

The smallest box in a work breakdown structure. It can be costed, timed and owned.

Think of it like

It is like one slice of the pizza. It is the piece one person picks up.

Example

In a house project, "fit the kitchen units" is one work package. Jack owns it, and it costs 4,000 pounds.

Why it matters

Estimates and progress reports are built up from work packages. Get them right and the totals follow.

Definition

A work package is the smallest piece of work in a work breakdown structure. It sits at the bottom of the tree. It is small enough to cost, to time and to give to one owner. The team plans its tasks inside it. Progress is tracked at this level, one package at a time.
The work packages are the boxes at the very bottom. Each one has an owner and a price.

Common mistake

Making packages too big to track. If nobody can say how far along one is, split it.

Key takeaways

  1. 1
    One owner. A single person answers for it.
  2. 2
    Costable. Small enough to price well.
  3. 3
    Trackable. You can tell when it is done.