Business Case and Charter
Level 3 Β· Starting a project
Why a project needs a business case before any money is spent. How a short signed charter then starts the project and hands the manager power.
Course contentsLesson 6 of 11
Level 1 Β· What a project is
Level 2 Β· Who runs a project
Level 3 Β· Starting a project
Level 4 Β· The life of a project
Level 5 Β· Ways to run a project
After this lesson you can
- Say what a business case must hold
- Work out a simple payback time
- Explain what a charter gives the manager
11 mincovers 2 glossary entries
Worth reading first: Project Sponsor and PMO
Why a project needs a business case and a charter
A business case is the paper that says why a project is worth its cost. It comes before any money is spent. A good one names the problem, compares two or three options and shows the cost and gain of each. A system that costs 80,000 dollars and saves 30,000 a year pays for itself in under three years.
One of the options should always be doing nothing. It sounds odd, but it is the honest yardstick. If doing nothing costs little, the project has to beat that. If doing nothing costs a lot, the case gets much easier to make.
The business case is checked again during the project, not filed away. Costs grow and needs change. If the reasons stop holding, the right move is to stop the project. A business case read only once was a request for money, not a reason.
A project charter is the short paper that starts the project. It names the goal, the sponsor and the project manager. It lists the main limits, such as the budget and the end date. The sponsor signs it, and from then on the work is official.
The charter's real job is handing over power. Before it is signed, the project manager cannot book people or spend money. After it, they can, inside the limits it sets. That is why it is short: one to three pages, not a full plan.
So the order runs like this. The business case asks for the money. Leaders read it and say yes or no. If they say yes, the charter starts the project and puts someone in charge. The detailed plan comes after.
The common mistake is packing the charter with the whole plan. Then it takes weeks to sign, and the project waits. The charter starts the work. The detail belongs in the plan that follows it.
Worked example
Emma makes the case for a booking system
Emma's clinic loses about 30,000 dollars a year to missed visits. A new booking system with text reminders would cost 75,000 dollars.
If it stops most of those losses, it pays for itself in 2.5 years. Doing nothing costs 30,000 dollars every year. The sponsor signs a two-page charter the next Monday.
The words for this lesson2
Check yourself
What does signing a project charter do?
Finished this lesson?