Skip to content
BENIBIX Learn

PRINCE2 and the PMBOK Guide

Level 5 Β· Ways to run a project

The two best-known names in project management. How PRINCE2 is a method with set roles and stages, while the PMBOK Guide is a guide you pick from.

Course contentsLesson 11 of 11

After this lesson you can

  • Say what PRINCE2 sets out
  • Describe how the PMBOK Guide is built
  • Explain why both must be tailored

12 mincovers 2 glossary entries

Worth reading first: Waterfall, Agile and Hybrid

How PRINCE2 and the PMBOK Guide differ

PRINCE2 and the PMBOK Guide are the two best-known names in project management. PRINCE2 is a method: it sets out roles, stages and steps to follow. The PMBOK Guide is a guide: it describes good practice and leaves the choices to you. PRINCE2 has 7 principles. The current PMBOK Guide has 6.

PRINCE2 began with the UK government. Its name stands for PRojects IN Controlled Environments. The latest version, the seventh, came out in 2023. It has seven principles, seven practices and seven processes. The practices used to be called themes.

The heart of PRINCE2 is control by stages. A project board, led by the person paying, approves one stage at a time. The project manager runs that stage inside set limits of time and money. They only go back to the board when a limit is about to break.

The PMBOK Guide comes from PMI, the Project Management Institute. Its eighth edition came out in November 2025. It rests on six principles and seven performance domains. A domain is one area to look after. Scope, schedule, finance and risk are four of them.

It also lists 40 processes, grouped under five focus areas from starting to closing. They are ideas to choose from, not steps you must take. The seventh edition, from 2021, had 12 principles and 8 domains and left the processes out. The eighth brought them back as options.

Both say the same thing about size: tailor it. PRINCE2 says so in one of its own principles. A three-week project does not need every form a three-year one does. Using the full set on a small job is the fastest way to make people hate the method.

The common mistake is treating them as rivals you must choose between. Many teams use PRINCE2's stages and board, and read the PMBOK Guide for its ideas on scope or risk. They answer different questions: how to run this project, and what good practice looks like.

Which one to reach for

  1. 1

    Reach for PRINCE2

    When you want set roles, set stages and a board that approves each one,.

  2. 2

    Reach for the PMBOK Guide

    When you want to see what good practice looks like and pick the parts that fit your project.

In PRINCE2 the board sets limits for each stage. The manager only goes back up when a limit will break.

Worked example

Jack's council library

Jack runs a new library for a city council in the UK, using PRINCE2. The board approves 4 stages, one at a time, each with a limit of plus or minus 10% on cost.

In stage 3 the cost is heading 15% over. That breaks the limit, so Jack takes it to the board. For the risk work, his team borrows ideas from the PMBOK Guide.

The words for this lesson2

Check yourself

What is the main difference between PRINCE2 and the PMBOK Guide?

Finished this lesson?

Marking it complete also marks its 2 glossary entries learned, which updates your roadmap and your saved page. 0 are already marked.