Project Life Cycle and Phases

Level 4 Β· The life of a project

The phases a project moves through, from the first idea to the close. How a phase gate stops spending on a bad idea before it costs more.

Course contentsLesson 8 of 11

After this lesson you can

  • Name the four common phases
  • Explain what a phase gate decides
  • Tell the project from the product's life

10 mincovers 3 glossary entries

Worth reading first: Project Plan and Kickoff

What the phases of a project are, and why gates sit between them

The project life cycle is the set of phases a project moves through. A common shape has four: start, plan, do and close. Each phase makes something the next one needs. Between phases sits a check, where leaders decide whether to go on. A house build might run design, permits, building and handover.

A project phase is one block of linked work with its own goal. It ends with something you can show, such as a design, a test result or a finished part. Phases often run one after another, but some can overlap when the work allows it.

Phases make a big job easier to handle. A two-year project is too large to plan in detail on day one. A three-month phase is not. So the team plans the next phase closely and leaves the later ones rough.

A phase gate is the check at the end of a phase. Leaders look back at the work just done and ahead at the plan for the next phase. Then they choose: go on, change course or stop. A gate is also called a kill point, because stopping is a real answer.

Gates matter because money grows with each phase. Stopping a bad idea after the design costs little. Stopping it after the building has started costs far more. Each gate is a cheap chance to stop before the next big spend.

The names change from field to field. Software might say discover, build, test and release. Building might say design, permit, build and hand over. The pattern is the same: every project starts, runs through its phases and ends.

The common mistake is mixing up the project's life with the product's life. The project ends at handover. The road, the app or the school then lives on for years, run as daily work by someone else.

Every project starts, runs and ends. A gate between each phase is a chance to go on, change course or stop.

Worked example

A toy maker's three gates

Lucy's toy company has 5 new toy ideas at its first gate. Each passes only if a cheap model tests well with children.

Only 2 ideas pass the second gate, where the cost to build is checked. Only 1 reaches the shops. The 4 that stopped early cost far less than one failed launch.

The words for this lesson3

Check yourself

Why is a phase gate also called a kill point?

Finished this lesson?

Marking it complete also marks its 3 glossary entries learned, which updates your roadmap and your saved page. 0 are already marked.