Analogous Estimating

Business📅 Scope, Schedule & CostProject Schedule

Also known as Top-Down Estimating, Analogous Estimate

A fast guess. It copies the time or cost of a past project like this one.

Think of it like

It is like guessing a trip will take three hours. A trip just like it took three hours last year.

Example

Last year's office move took 8 weeks. This one is a little bigger, so Lucy guesses 10 weeks.

Why it matters

It gives a number on day one, long before the detail exists to do better.

Definition

Analogous estimating uses a past project that was like this one. You take how long it took or what it cost, and use that as your guess. You may adjust it for size or for what is different. It is fast and cheap to do, but it is rough. It works best early on, when few details are known.
Analogous is the first panel. One past project becomes the guess, so it is quick and rough.

Common mistake

Using a past project that only looks the same. If the team, size or tools differ, the guess is off.

Key takeaways

  1. 1
    Past project. Start from something done before.
  2. 2
    Fast. Minutes, not days.
  3. 3
    Rough. Good for early, not for final.