📅Float
Also known as Slack Time, Total Float, Free Float
How long a task can slip before it makes the project late.
Think of it like
It is like leaving for the bus ten minutes early. You can stop to tie your shoe and still catch it.
Example
Painting the fence takes 2 days, and it has 3 days of float. It can start up to 3 days late with no harm.
Why it matters
It shows where you can move people and dates without hurting the end date.
Formula
Total float = latest start - earliest startDefinition
Common mistake
Key takeaways
- 1Total float. The slip before the end date moves.
- 2Free float. The slip before the next task moves.
- 3Shared. Tasks on one path draw on the same float.