Float

Business📅 Scope, Schedule & CostProject Schedule

Also known as Slack Time, Total Float, Free Float

How long a task can slip before it makes the project late.

Think of it like

It is like leaving for the bus ten minutes early. You can stop to tie your shoe and still catch it.

Example

Painting the fence takes 2 days, and it has 3 days of float. It can start up to 3 days late with no harm.

Why it matters

It shows where you can move people and dates without hurting the end date.

Formula

Total float = latest start - earliest start

Definition

Float is how long a task can slip before it delays something else. Total float is how long it can slip before the project ends late. Free float is how long it can slip before the next task must move. Tasks on the critical path have zero float. Float belongs to the whole path, so using it up on one task leaves less for the rest.
Order parts ends 3 days before test needs it. Those 3 days are its float.

Common mistake

Treating float as free time for one task. Spend it early, and the rest of the chain has none left.

Key takeaways

  1. 1
    Total float. The slip before the end date moves.
  2. 2
    Free float. The slip before the next task moves.
  3. 3
    Shared. Tasks on one path draw on the same float.