Cycle Time

Business📋 Agile DeliveryKanban

Also known as Flow Time

The time from when work on an item starts until it is finished. Waiting before the start does not count.

Think of it like

It is like timing a cook from the start of your pizza to the end. The wait before does not count.

Example

For the same report, work starts on 10 March and ends on 14 March. The cycle time is 4 days, inside a 13-day lead time.

Why it matters

It shows how long the team's own process takes. Fewer items in progress is the surest way to shorten it.

Formula

Cycle time = date finished - date started

Definition

Cycle time is how long a piece of work takes from when work on it starts until it is finished. It leaves out the time the item waited before anyone picked it up. It shows how fast the team moves work once it begins. Shorter and steadier cycle times make dates easier to predict. Kanban counts it as one of its core flow measures.
Cycle time is the short bar. It only starts when someone begins the work, so it is 4 days, not 13.

Common mistake

Using one name for two different clocks. Say where your timer starts, or two teams will compare different things.

Key takeaways

  1. 1
    Starts at the start. The clock begins when work begins.
  2. 2
    Ends at done. It stops when the item is finished.
  3. 3
    Watch the spread. Steady times make plans easier.