📋Throughput
Also known as Delivery Rate
How many items a team finishes in a set time. For example, five items a week.
Think of it like
It is like counting the cakes a shop sells each day. Not the ones in the oven, just the ones sold.
Example
Over six weeks, a team finishes 4, 6, 5, 5, 4 and 6 items. Its throughput is about 5 a week, so 20 more items should take about 4 weeks.
Why it matters
It turns past work into a simple forecast. Counting items is quicker than guessing how big each one is.
Formula
Average work in progress = average throughput x average cycle time (Little's Law)Definition
Common mistake
Key takeaways
- 1Count finished items. Only done work counts.
- 2Per unit of time. Items per day or per week.
- 3Forecast from it. Past pace predicts the next weeks.